Wellcome to National Portal
Text size A A A
Color C C C C

সর্ব-শেষ হাল-নাগাদ: ২৪ মার্চ ২০২২

মহেশখালী-আনোয়ারা গ্যাস সঞ্চালন সমান্তরাল পাইপলাইন নির্মাণ প্রকল্প

Project Director: Md. Ariful Haque Fakir
Project Name: Maheshkhali-Anowara Parallel Pipeline Project
E-Mail: mapgtcl@gmail.com
Cell No.: 01709639726

 

 

Project Name: Maheshkhali-Anowara Parallel Pipeline Project
Implementation Period: July 2016 to June 2021
Project Cost Tk. 1314.72 crore

Source of Finance: GTCL own fund

  • Land Acquisition/Requisiton:
  • Coxbazar District:

Proposal for Land Acquisition and Requisition was sent to DC ofiice, Coxbazar on 12.04.2017 and handover of Land completed on December 2018.

  • Chittagong District:

Proposal for Land Acquisition and Requisition was sent to DC ofiice, Coxbazar on 12.04.2017 and handover of Land completed on March 2019. Preparation of estimate for Land Requisition is under process under Chattogram District.

  • Procurement of Pipeline Materials & Equipment:

All Materials (Line Pipes, Coating & Wrapping Materials, Induction Bends, Miscellaneous Fittings, Pig Traps, Cathodic Protection (CP) Materials and Thermo Electric Generator (TEG), Ball Valves & Gate Valves and Plug Valves) under the project had been completed.

  • Construction of Pipeline:

To accomplish the construction work, 79 Km pipeline construction work has divided into 5(Five) lot/section and individual contract agreement signed with contractors for each section on 20-02-2018. Construction of 79 Km pipeline completed and after successful completion of Commissioning activities LNG is being evacuating to the National Gas Grid through this newly constructed pipeline from 22 February 2020.

  • 3 nos. River and 4 nos. Khal Crossing by HDD Method:

To accomplish the construction work, two individual contracts was signed with Gypsum – GasMin JV and Punj Lloyd Limited and Pipeliners Consortium on 11-01-2018 and 18-01-2018 respectively. All the HDD crossings completed on 26 October 2019.

  • Installation of 1200 MMSCFD Capacity CTMS at Anowara:

To accomplish the construction of mentioned CTMS on EPC/Turn-Key basis, a contract was signed with Metron-PEAL JVCA on 17-04-2018. Installation along with Leak Test completed on 9 October 2019.

 



COVID19 Movement Pass Online Police Clearance BD Police Help line Expatriate Cell Opinion or Complaint NIS Bangladesh Police Hot Line Number Right to Information PIMS Police Cyber Support for Women BPWN Annual Training Workshop Achievement & Success PHQ Invitation Card
Press Release Recruitment Information Procurement / Tender Notice Legal Instrument Innovation Corner Detective Magazine Bangladesh Football Club Diabetes-Covid19 Exam Results Accident Info Important Forms

Apps

icon icon icon icon icon icon