Project Director: Md. Ariful Haque Fakir
|
Project Name: Maheshkhali-Anowara Parallel Pipeline Project
Implementation Period: July 2016 to June 2021
Project Cost Tk. 1314.72 crore
Source of Finance: GTCL own fund
Proposal for Land Acquisition and Requisition was sent to DC ofiice, Coxbazar on 12.04.2017 and handover of Land completed on December 2018.
Proposal for Land Acquisition and Requisition was sent to DC ofiice, Coxbazar on 12.04.2017 and handover of Land completed on March 2019. Preparation of estimate for Land Requisition is under process under Chattogram District.
All Materials (Line Pipes, Coating & Wrapping Materials, Induction Bends, Miscellaneous Fittings, Pig Traps, Cathodic Protection (CP) Materials and Thermo Electric Generator (TEG), Ball Valves & Gate Valves and Plug Valves) under the project had been completed.
To accomplish the construction work, 79 Km pipeline construction work has divided into 5(Five) lot/section and individual contract agreement signed with contractors for each section on 20-02-2018. Construction of 79 Km pipeline completed and after successful completion of Commissioning activities LNG is being evacuating to the National Gas Grid through this newly constructed pipeline from 22 February 2020.
To accomplish the construction work, two individual contracts was signed with Gypsum – GasMin JV and Punj Lloyd Limited and Pipeliners Consortium on 11-01-2018 and 18-01-2018 respectively. All the HDD crossings completed on 26 October 2019.
To accomplish the construction of mentioned CTMS on EPC/Turn-Key basis, a contract was signed with Metron-PEAL JVCA on 17-04-2018. Installation along with Leak Test completed on 9 October 2019.