Project Director: Mohammad Zakirul Islam |
The objectives of the project are :
(i) To acclerate the socio-economic developement of the country by evacuating Re-gasified Liquefied Natural Gas (RLNG) to be received at Maheshkhali to national gas grid.
(ii) To construct a 42″diameter 7 km Gas Transmission pipeline from Maheshkhali Zero Point (Kaladia Char) to CTMS (Dhalghat Para) and hookup with under construction 42″ diameter Maheshkhali-Anowara Parallel Pipeline to supply RLNG to National gas grid.
(iii) To meet the Gas demand of gas based power plants and Industries including other consumers.
Implementation Period: October 2018 to March 2021 .
DPP approval Date: 28-10-2018
Source of Finance: GTCL Own Fund
Project Cost: Tk. 30,177.00 Lac