Objective of the Project: The SCADA Rehabilitation Project is being implemented with the objective to rehabilitate and expand the existing Company’s SCADA System for the centralized monitoring and smooth operation of the gas production, transmission and distribution.
Implementation Period: July 2012 to December 2018
Source of Finance: GoB and JICA
Project Cost: Local currency Tk. 5,376.90 Lac and Foreign currency: Tk. 24,023.55 Lac Totaling Tk. 29,400.45 Lac.
Progress of Project Implementation: The SCADA Rehabilitation Project has been undertaken to rehabilitate and expand the existing Company’s SCADA System for the centralized monitoring and smooth operation of the gas grid. Contract has been signed on 4-2-2016 with EPC contractor Yokogawa India Ltd for installation of SCADA System. The Contractor has completed the design works under supervision of the Project officials. Works are in progress for construction of RTU Room, Radio Room and Demra Control Center, and renovation of Ashuganj Auxiliary Control Center is in progress. Contractor has completed decoration of Head Office Control Center. Besides these, the Contractor has already imported Instruments, RTU, Flow Computer, Battery, RTU Charger, UPS Cell Panel, Network Management System, VOIP Phone, Video Conference Unit, Server, Workstation and all related Software. Installation of RTUs in RTU Rooms and instrumentation works in the site will commence shortly. On completion of all works of the projects, it will be possible to observe the produced gas from the gas fields, gas transmission in the national gas grid and gas pressure & flow of gas to the bulk consumers.